Guide to DCP Study Close-Out
Milestone 1: Study Accrual Nearing Completion
Close-out Tasks appearing under each milestone are generally initiated in the same timeframe. Click on the Timing Reminders and Forms & Resources tabs for more information.
View All
- Estimate when each enrolling site will complete accrual and each site’s last participant will go off study.
- Ensure the CLO Monitors are scheduling each PO close-out visit to occur close to when the PO’s last participant completes the study.
- Schedule a call with the DCP Monitoring Contractor to discuss preparations for database lock.
- Discuss an expected date for submission of the draft manuscript with the Protocol PI and DCP Medical Monitor.
The draft manuscript is due to the DCP-PIO and DCP Medical Monitor within 120 calendar days when:
a. All participants have met the primary study endpoint, and
b. At least 80% of participants are off-study.
Key to common acronyms: DCP Consortia Acronym List, (doc 61kb)
Provide feedback on the Guide to DCP Study Close-Out.